The City of Sioux City Engineering Division announces the start of the South Rustin Street Reconstruction – Dodge Avenue to Leech Avenue Project. The contractor, RP Constructors LLC, plans to begin construction on or about June 16, 2022 and construction shall be completed within 95 working days, which is anticipated to be in November of 2022. This project includes the complete street paving replacement, replacement of water, storm, and sanitary utilities.
Construction will be completed in one stage with a full closure of South Rustin Street between Dodge Avenue and Leech Avenue, sidewalk access will be maintained through the project. A detour route along South Fairmount Street, Dodge Avenue, and Jay Avenue will be posted during the closure.
Motorists are advised to reduce speed, drive cautiously, and obey all traffic control signs with regards to this closure.