Quantcast

Sioux City Times

Friday, November 15, 2024

South Rustin Street Reconstruction Project - Dodge Avenue to Leech Avenue

Sioux

The City of Sioux City Engineering Division announces the start of the South Rustin Street Reconstruction – Dodge Avenue to Leech Avenue Project. The contractor, RP Constructors LLC, plans to begin construction on or about June 16, 2022 and construction shall be completed within 95 working days, which is anticipated to be in November of 2022. 

This project includes the complete street paving replacement, replacement of water, storm, and sanitary utilities. Construction will be completed in one stage with a full closure of South Rustin Street between Dodge Avenue and Leech Avenue, sidewalk access will be maintained through the project. A detour route along South Fairmount Street, Dodge Avenue, and Jay Avenue will be posted during the closure.

Motorists are advised to reduce speed, drive cautiously, and obey all traffic control signs with regards to this closure.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS